In this paper we study the Resource Constrained Project Scheduling Problem (RCPSP) with "Feeding Precedence" (FP) constraints and minimum makespan objective. This problem typically arises in production planning environment, like make-to-order manufacturing, where the effort associated with the execution of an activity is not univocally related to its duration percentage and the traditional finish-to-start precedence constraints or the generalized precedence relations cannot completely represent the overlapping among activities. In this context, we need to introduce in the RCPSP the FP constraints. For this problem we propose a new mathematical formulation and define a lower bound based on the Lagrangian relaxation of the resource constraints. A computational experimentation on randomly generated instances of sizes of up to 100 activities shows a better performance of this lower bound when compared to other lower bounds. Moreover, for the optimally solved instances, its value is very close to the optimal one. Furthermore, in order to show the effectiveness of the proposed lower bound on large instances for which the optimal solution is known, we adapted our approach to solve the benchmarks of the basic RCPSP from the PSLIB with 120 activities.

Bianco, L., Caramia, M. (2011). Minimizing the completion time of a project under resource constraints and feeding precedence relations: a Lagrangian relaxation based lower bound. 4OR, 9(4), 371-389 [10.1007/s10288-011-0168-6].

Minimizing the completion time of a project under resource constraints and feeding precedence relations: a Lagrangian relaxation based lower bound

BIANCO, LUCIO;CARAMIA, MASSIMILIANO
2011-01-01

Abstract

In this paper we study the Resource Constrained Project Scheduling Problem (RCPSP) with "Feeding Precedence" (FP) constraints and minimum makespan objective. This problem typically arises in production planning environment, like make-to-order manufacturing, where the effort associated with the execution of an activity is not univocally related to its duration percentage and the traditional finish-to-start precedence constraints or the generalized precedence relations cannot completely represent the overlapping among activities. In this context, we need to introduce in the RCPSP the FP constraints. For this problem we propose a new mathematical formulation and define a lower bound based on the Lagrangian relaxation of the resource constraints. A computational experimentation on randomly generated instances of sizes of up to 100 activities shows a better performance of this lower bound when compared to other lower bounds. Moreover, for the optimally solved instances, its value is very close to the optimal one. Furthermore, in order to show the effectiveness of the proposed lower bound on large instances for which the optimal solution is known, we adapted our approach to solve the benchmarks of the basic RCPSP from the PSLIB with 120 activities.
2011
Pubblicato
Rilevanza internazionale
Articolo
Esperti anonimi
Settore MAT/09 - RICERCA OPERATIVA
English
Con Impact Factor ISI
Feeding precedence relations; Lagrangian relaxation; Lower bound; RCPSP
Bianco, L., Caramia, M. (2011). Minimizing the completion time of a project under resource constraints and feeding precedence relations: a Lagrangian relaxation based lower bound. 4OR, 9(4), 371-389 [10.1007/s10288-011-0168-6].
Bianco, L; Caramia, M
Articolo su rivista
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/2108/23407
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 22
  • ???jsp.display-item.citation.isi??? 20
social impact