In this note we show how to manage, by means of Generalized Precedence Relationships, some kinds of temporal constraints introduced by Chen et al. (1997) in project networks.

Caramia, M., Guerriero, F. (2011). A Note on the modeling of project networks with temporal constraints. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 211(3), 666-670 [1016/j.ejor.2010.12.020].

A Note on the modeling of project networks with temporal constraints

CARAMIA, MASSIMILIANO;
2011-01-01

Abstract

In this note we show how to manage, by means of Generalized Precedence Relationships, some kinds of temporal constraints introduced by Chen et al. (1997) in project networks.
2011
Pubblicato
Rilevanza internazionale
Articolo
Esperti anonimi
Settore MAT/09 - RICERCA OPERATIVA
English
Con Impact Factor ISI
Project network; Project scheduling; Time constraints
Caramia, M., Guerriero, F. (2011). A Note on the modeling of project networks with temporal constraints. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 211(3), 666-670 [1016/j.ejor.2010.12.020].
Caramia, M; Guerriero, F
Articolo su rivista
File in questo prodotto:
File Dimensione Formato  
EJOR2.pdf

solo utenti autorizzati

Licenza: Copyright dell'editore
Dimensione 517.79 kB
Formato Adobe PDF
517.79 kB Adobe PDF   Visualizza/Apri   Richiedi una copia

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/2108/23396
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 5
  • ???jsp.display-item.citation.isi??? 4
social impact