We study the problem of levelling resources in a project with generalized precedence relationships, given a deadline for the completion of all the activities and variable execution intensities and flexible durations of the activities. Variable execution intensities have been taken into account firstly by Kis in 2005 applied to a real world scenario in which, due to the physical characteristics of some manufacturing processes, the effort associated with a certain activity for its execution may vary over time. Generalized precedence relationships and variable intensity execution and duration have not been dealt with together to the best of our knowledge. For this novel problem we propose a mixed integer linear programming formulation, a lower bound based on Lagrangian relaxation, and a branch and bound algorithm. Computational results on known benchmarks are provided.

Bianco, L., Caramia, M., Giordani, S. (2016). Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities. OR SPECTRUM, 38(2), 405-425 [10.1007/s00291-016-0435-1].

Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities

BIANCO, LUCIO;CARAMIA, MASSIMILIANO;GIORDANI, STEFANO
2016-01-01

Abstract

We study the problem of levelling resources in a project with generalized precedence relationships, given a deadline for the completion of all the activities and variable execution intensities and flexible durations of the activities. Variable execution intensities have been taken into account firstly by Kis in 2005 applied to a real world scenario in which, due to the physical characteristics of some manufacturing processes, the effort associated with a certain activity for its execution may vary over time. Generalized precedence relationships and variable intensity execution and duration have not been dealt with together to the best of our knowledge. For this novel problem we propose a mixed integer linear programming formulation, a lower bound based on Lagrangian relaxation, and a branch and bound algorithm. Computational results on known benchmarks are provided.
2016
Pubblicato
Rilevanza internazionale
Articolo
Esperti anonimi
Settore MAT/09 - RICERCA OPERATIVA
English
Con Impact Factor ISI
Project scheduling, Generalized precedence relationships, Resource levelling.
http://link.springer.com/article/10.1007/s00291-016-0435-1
Bianco, L., Caramia, M., Giordani, S. (2016). Resource levelling in project scheduling with generalized precedence relationships and variable execution intensities. OR SPECTRUM, 38(2), 405-425 [10.1007/s00291-016-0435-1].
Bianco, L; Caramia, M; Giordani, S
Articolo su rivista
File in questo prodotto:
File Dimensione Formato  
OR_Spectrum_2016.pdf

solo utenti autorizzati

Licenza: Copyright dell'editore
Dimensione 735.28 kB
Formato Adobe PDF
735.28 kB Adobe PDF   Visualizza/Apri   Richiedi una copia

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/2108/142210
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 30
  • ???jsp.display-item.citation.isi??? 25
social impact